Principal Contractor case study

Meadowlands
Multi-Phase Residential Development

A project that developed from an initial garage demolition and client cabin into a pool house and gym, followed by demolition of the existing residence and delivery of the new main home, with DMP Buildtech coordinating the wider works and trades as Principal Contractor.

Project overview

One appointment that developed into three major phases.

DMP Buildtech was originally appointed to demolish a prefab double garage and construct a cabin to accommodate the client during later works. The project then progressed into the pool house and gym before expanding again to include demolition of the original main residence and construction of the replacement home.

Principal Contractor

Managing a changing, multi-phase residential build.

The role extended beyond individual construction packages. DMP Buildtech coordinated site activity and liaised with the other trades as the programme developed through the cabin, pool house and gym, and ultimately the new main residence.

Residential development · Principal Contractor

Three project phases

Cabin. Pool house & gym. Main residence.

The photographic record documents how the appointment expanded from a relatively contained enabling project into a substantial residential development.

01 · Cabin

Client accommodation

Following demolition of the prefab garage, a new cabin was constructed to provide accommodation for the client during the later main-house works.

02 · Pool house & gym

Second phase

The works progressed into construction of the pool-side building and gym, including associated groundworks and building works.

03 · Main residence

New home

The existing dwelling was demolished and replaced with the new residence, with DMP Buildtech continuing its Principal Contractor coordination role.

Scope & delivery

Principal Contractor capability demonstrated across the site.

01Prefab double garage demolition and site preparation
02Client cabin constructed as the first phase
03Pool house and gym construction progressed as a second phase
04Drainage, groundworks and structural building activity coordinated
05Existing main residence demolished for redevelopment
06New residence delivered with liaison and coordination of other trades

Planning a substantial residential project?